Construction of a new electric bus depot in St. Petersburg is delayed.

The Accounts Chamber Commission: The electric bus depot in Rzhevka will not be completed by the end of 2026.

The Audit Chamber reached these conclusions after inspecting the construction. Some work is more than a year behind schedule and approximately 15% complete.

Construction of a new electric bus depot in St. Petersburg is delayed.
Фото: Administration of the Krasnogvardeisky District of St. Petersburg, source: t.me/krgv_live

A commission from the Audit Chamber (Accounts Chamber) reviewed the progress of construction of the electric bus depot in Rzhevka and concluded that the project will not be completed by the original deadline. All work was supposed to be completed by the end of 2026, but these plans now appear unrealistic.

Smolny stated that construction is being carried out in two phases. According to the Audit Chamber's estimates, work on the first phase is 80% complete, while work on the second phase, scheduled for completion in 2026, is only 15% complete. Some work is one or even two years behind schedule.

"According to experts, timely completion of the work will not be ensured due to the bankruptcy of the contractor," the Audit Chamber added.

Rosselkhoznadzor (Federal Service for Veterinary and Phytosanitary Surveillance) in St. Petersburg is blocking a shipment of peanuts from entering the country due to the risk of cholera spread.

St. Petersburg received another batch of new buses, this time 30 units.

Author: Наталья Чудесатова

By continuing to use our website, you consent to the processing of cookies that ensure the proper website operation.Accept